Port Development Plan

tt

Phases of port development plan:

 description Year Phase

  *Approximately 1650 m of breakwater extention,construction of two container berth(640m) and three multi-purpose berth(540m)

*17 milion m3  dredging to(-16m) depth

*Reclamation of 195 heactares by sediment 

 2017 1
Construction of a container berth(360m) 2018 2
 Construction of an oil berth 2020 3
 Construction of a multi-purpose berth
 2020 4
 Construction of a container berth (360m) 2024 5