Phases of port development plan:
description | Year | Phase |
*Approximately 1650 m of breakwater extention,construction of two container berth(640m) and three multi-purpose berth(540m) *17 milion m3 dredging to(-16m) depth *Reclamation of 195 heactares by sediment | 2017 | 1 |
Construction of a container berth(360m) | 2018 | 2 |
Construction of an oil berth | 2020 | 3 |
Construction of a multi-purpose berth
| 2020 | 4 |
Construction of a container berth (360m) | 2024 | 5 |